Owned by the citizens of Mason County, Oakview is your medical care facility, offering a broad range of high quality, long-term health care services and enriching the lives of those we serve. We recognize our responsibility as a public, nonprofit entity to serve our community and welcome all who seek our care.

We strive to create a home-like environment that upholds each resident’s quality of life, with a skilled medical staff, pleasant surroundings, carefully prepared meals, engaging social activities, a variety of rehabilitative therapies, a family support center and much more. For more information or to schedule a tour please contact us.

Be sure and “like” our Facebook page, just click the Facebook link at the top right of the page or paste the address into your web browser,  www.facebook.com/oakviewmcf

REQUEST FOR PROPOSALS FOR ARCHITECT / ENGINEERING DESIGN SERVICE AND

CONSTRUCTION MANAGER SERVICES

Oakview Medical Care Facility (“Owner”) will receive qualifications and proposals for

ARCHITECT / ENGINEER (A/E) DESIGN SERVICES AND

CONSTRUCTION MANAGER (CM)

OF A PROPOSED ADDITION AND RENOVATIONS PROJECT FOR

 OAKVIEW MEDICAL CARE FACILITY

1001 DIANA ST. LUDINGTON, MI 49431

until 2:00 pm EST January 22nd, 2020.  Electronic versions of the RFP Documents can be found here:

A/E Design RFP Document Link

https://app.e-builder.net/public/publicLanding.aspx?QS=943f787e2ecb41eca899c5dc393fb0df

Construction Manager RFP Document Link

https://app.e-builder.net/public/publicLanding.aspx?QS=3443a333e33246a2a3d96e793d92e7c6

Request for Proposal documents can also be obtained at the offices of Plante Moran Living Forward, 27400 Northwestern Highway, Southfield, MI 48034 starting January 6th, 2020 at 1:00 pm.  Please contact Eric Dumont by email at eric.dumont@plantemoran.com for additional information and/or any questions.

A pre-bid walk thru at the facility is currently scheduled for January 13, 2020 starting at 1:00pm EST.  Please plan to meet at the front entrance of the facility.

Owner reserves the right to reject any or all proposals, waive any irregularities therein and accept the proposal, which will best serve Owner’s interest.

Oakview Medical Care Facility
New Addition and Renovation Project
REQUEST FOR PROPOSAL (RFP) – ARCHITECT ENGINEERING DESIGN SERVICES
ADDENDUM #1
JANUARY 17, 2020

FROM: Eric Dumont
Plante Moran Living Forward
26400 Northwestern Highway
Southfield, MI 48076

TO: Respective Bidders

ADDENDUM FOR: AE RFP for Oakview Medical Care Facility – New Addition and
Renovation Project.

CLARIFICATION:
Please acknowledge the following addendum on the bid form and include the changes:

A. REVISED RFP DUE DATE / TIME LINE:
1. Revised RFP Due Date: The RFP due date has been extended to January 30, 2020
at 2:00pm. Please submit all responses accordingly per the details within the
RFP by no later than the date and time listed above.
2. Pre‐Bid Walk thru Sign‐In Sheet: Please reference attached

B. REVISED RFP DOCUMENTS:
1. Revised C.1 – B101‐2017, As Modified – Revised with Final Owner Legal Review
Comments
2. Revised C.2 – A201‐2007, As Modified – Revised with Final Owner Legal Review Comments

C. REQUEST FOR INFORMATION CLARIFICATION:
1. Question: Is there accurate CAD or Revit files that will be provided for existing
architecture, site, mechanical and electrical conditions for the project? Or will
the facility need to be field verified?
Response: There are no CAD files available currently for the existing facility. We
will be able to provide PDF versions of existing drawings; however, it is
All rights reserved. Intellectual Property of Plante Moran Living Forward
recommended that the A/E complete a field verification of the areas to be
renovated.
2. Question: The budget currently has any breakdown for courtyard, addition and
renovation that can be provided?
Response: The preliminary budget was not broken down into these specific
categories.
3. Question: Is there a scope of work that has been defined for technology that
needs to be upgraded or integrated into the project or is that work to be
programmed in schematics by our consultant.
Response: This will need to be further reviewed and identified as a part of the SD
process. Initial response is that it will be minimal from a design perspective – i.e.
– relocation of existing equipment, data/voice drops, and minor added AV
equipment.
4. Question: Is there a scope of work that has been defined for the kitchen
upgrades that needs to be renovated/upgraded into the project or is that work
to be programmed in schematics by our consultant
Response: This will need to be further reviewed and identified as a part of the SD
process. Initial response is that it will be minimal from a design perspective – i.e.
– new walk in freezer / fridge area and general cosmetic upgrades to the kitchen
flooring/walls.
5. Question: Page 5 of the RFP, Section 3D – Relevant Firm / Team Experience
Summary matrix requests detailing all project your firm has completed in the last
5 years. Are you seeking skilled nursing facility projects only, also additional
relevant healthcare projects?
Response: Please provide both past experiences.
6. Question: Is a topo survey required by the A/E?
Response: No, this will be provided by the owner.
7. Question: Should we assume the project requires site plan submission to the
local covering authority?
Response: Yes.
8. Question: Should we assume that the facility’s electrical service has capacity for
the additions and renovations?
Response: Yes.
9. Question: Is there a generator for the facility? If so, does it serve the entire
facility or only select loads? Also, should we assume that the generator has
capacity for additional load?Response: Yes, there is currently a full building system generator that has excess capacity available. The A/E will need to review the current load and design accordingly as needed for the new additions and renovations.
10. Question: Does the facility have boilers as the source for heating? No steam –
forced air? If so, does it service the entire facility? Also, should we assume that
the boiler(s) have capacity for additional load?
Response: Yes, there are currently several boilers throughout the facility that
serve radiant heat. There is additional capacity available from the boilers,
however the A/E will need to review the current load and design accordingly as
needed for the new additions and renovations.
11. Question: Should we assume separate HVAC systems for the additions, or does
the existing HVAC have capacity for the additional load?
Response: A 3rd party pre‐balance survey will be conducted on the existing HVAC
system. The A/E will be required to evaluate that report and review the
condition of the existing equipment in order to determine if the existing system
has capacity for additional load. If the system cannot handle the added load,
then the A/E should assume it will have to design a HVAC system as a part of the
design process.
12. Question: Will there be a kitchen consultant (either by owner or the architect)
because it looks like the existing kitchen will be repurposes?
Response: The RFP and contract requires that the A/E provide the kitchen
consultant. This consultant will further meet with the owner and design team to
evaluate the design and equipment needs of the kitchen.
13. Question: Is the water service provided by municipal service? Is the sewer
service via a municipality? Is there separate storm water service?
Response: All water, storm, and sewer are City of Ludington. The A/E will need
to work with the City engineers and design a system that meets all requirements.

END OF ADDENDUM #1

 

Oakview Medical Care Facility
New Addition and Renovation Project
REQUEST FOR PROPOSAL (RFP) – CONSTRUCTION MANAGER SERVICES
ADDENDUM #1
JANUARY 17, 2020

FROM: Eric Dumont
Plante Moran Living Forward
26400 Northwestern Highway
Southfield, MI 48076

TO: Respective Bidders
ADDENDUM FOR: CM RFP for Oakview Medical Care Facility – New Addition and
Renovation Project.

CLARIFICATION:
Please acknowledge the following addendum on the bid form and include the changes:

A. REVISED RFP DUE DATE / TIME LINE:
1. Revised RFP Due Date: The RFP due date has been extended to January 30, 2020
at 2:00pm. Please submit all responses accordingly per the details within the
RFP by no later than the date and time listed above.
2. Pre‐Bid Walk thru Sign‐In Sheet: Please reference attached

B. REVISED RFP DOCUMENTS:
1. Revised C.1 – B101‐2017, As Modified – Revised with Final Owner Legal Review
Comments
2. Revised C.2 – A201‐2007, As Modified – Revised with Final Owner Legal Review
Comments
3. Added Exhibit I – Statutory Bond Forms – Provided by Owner Legal Team

C. REQUEST FOR INFORMATION CLARIFICATION:
1. Question: Can a blue lined version of the modifications of the AIA documents be
provided for further review.
Response: This cannot be provided at this time due to the AIA software and final
version provided by Owner Legal Comments.
All rights reserved. Intellectual Property of Plante Moran Living Forward
2. Question: If it could prove to save time and money, would you accept three
budgets instead of the four budgets outlined?
Response: Yes, please provide as an alternate option and include in the
clarification section of the RFP.

END OF ADDENDUM #1

Bed Availability

For information regarding bed openings at Oakview Medical Care Facility, please call our Admissions staff at (231)845-5185 (x227) for the most current availability.

Job Openings

We are looking for great people to add to our work family. See available positions here. Please fill out our job application if you would like to be considered.

In case of an Emergency at the Facility,
this is where you would find pertinent information.